Generation

Boss Clima Tower Something, something guide

Product name

Introduction

Please read this Userguide carefully. Please note that diagrams are for illustrative purposes only. User guides are also available - please contact us for more details.

BoSS mobile aluminium towers are light-weight scaffold towers used throughout the building and construction industry for both indoor and outdoor access solutions, where a stable and secure platform is required. Ideal for maintenance and installation work or short-term access, the highly versatile towers provide a strong working platform for a variety of heights.

This User Guide provides you with step by step instructions to ensure your system is assembled easily and safely using the 3T (Through The Trapdoor) method.

The law requires that personnel erecting, dismantling or altering towers must be competent. Any person erecting a BoSS mobile tower must have a copy of this guide. For further information on the use of mobile access and working towers, consult the PASMA operators‘ code of practice.

Handrail

Compliances

The BoSS Clima aluminum system has been tested and certified to EN 1004: 2004 Class 3. Instruction Manual EN 1298-IM-EN

Preparation & Inspection

Inspect the equipment before use to ensure that it is not damaged and that it functions properly. Damaged or incorrect components should not be used.

Safe Use

Lifting of Equipment

Stabilisers/Ballast

Movement

During Use

Wind DescriptionBeaufort ScaleBeaufort No.Speed in MPHSpeed In M/Sec
Medium BreezeRaises dust and
loose paper, twigs
snap off
48-124-6
Strong BreezeLarge branches in
motion, telegraph
wires whistle
625-3111-14
Gale ForceWalking is difficult839-4617-21

Ties

Maintenance - Storage - Transport

Diagram

Quantity Schedule - 1450 Width Towers

IMPORTANT: Please ensure you also read the other Quantity Schedules *If you are unable to position the working platform easily from the ground, you may heighten. Requires an additional fixed platform for this tower weight

Number Of Working Platforms Allowed

The maximum safe working load (the combined weight of the users, tools and materials) that may be placed on the tower is the total weight less than the self weight of the tower. The total weight for the towers shown in the schedule is 950kg.

Example 1: A 1450 tower built using the 3T method with a 4.2m platform height and a platform length of 1.8m has a self weight of 180kg.

950kg - 180kg = 770kg maximum safe working load total weight self weight (users, tools and materials)

Example 2: A 1450 tower built using the 3T method with a 11.7m platform height and a platform length of 2.5m has a self weight of 449kg.

950kg - 449kg = 501kg maximum safe working load total weight self weight (users, tools and materials)

For greater heights and loads, consult BoSS for guidance.

Platform Loading

On a 1450 tower, a platform may comprise of a single deck or two decks placed side by side. The maximum safe working load (the combined weight of the users, tools and materials) that may be placed on a platform is 275kg. This must be evenly distributed over either one deck, or two decks placed side by side.

The quantities on within the 1450 Width Tower Quantity Schedule will enable BoSS towers to be built safely and therefore comply with the requirements of the Work at Height Regulations. They include double guardrails to all platforms. Toeboards will need to be added if any levels are used as working platforms and for storage of materials. EN 1004 requires platforms at least every 4.2m, and these measures will exceed that requirement.

Ballast : Internal / External Use

There is no requirement for ballast on 1450 towers if using stabilisers as detailed in the table in the 1450 Width Towers Quantity Schedule.

Mobile Outriggers

MP16 outriggers can be used instead of SP15 stabilisers, as detailed below. Mobile outrigger kits comprise of:

Mobile Outrigger Kit
MP 16 Mobile Outrigger4
125/150/20mm Castor
(Use Same Diameter castors as on tower)
4
250mm Adjustable Leg4
Plan Braces4
The above components replace: SP15 Stabiliser4

Stabilisers

To improve rigidity, larger stabilisers can be used at a lower level than shown in the table within the 1450 width towers quantity schedule.

Angle Of Stabiliser 1450 Tower

Double Width 1450 Tower Dimension X

Platform Length 1.8mPlatform Length 2.5m
SP7X = 3351X = 3629
SP10X = 4789X = 5100
SP15X = 5520X = 5838

Quantity Schedule - 850 Width Towers

BoSS Clima 850 to EN 1004: Available in 2 lengths - 1.8m and 2.5m Internal/External Use - Towers under 2.5m are outside of the scope of EN 1004

IMPORTANT: Please ensure you also read the Quantity Schedule below.

BoSS Clima 850 to EN 1004: Available in 2 lengths - 1.8m and 2.5m Internal/External Use - Towers under 2.5m are outside of the scope of EN 1004

Number Of Working Platforms Allowed

The maximum safe working load (the combined weight of the users, tools and materials) that may be placed on the tower is the total weight less than the self weight of the tower. The total weight for the towers shown in the schedule is 950kg.

Example 1: A 850 tower built using the 3T method with a 4.2m platform height and a platform length of 1.8m has a self weight of 151kg

950kg - 151kg = 799kg maximum safe working load total weight self weight (users, tools and materials)

Example 2 A 850 tower built using the 3T method with a 11.7m platform height and a platform length of 2.5m has a self weight of 408kg.

950kg - 408kg = 542kg maximum safe working load total weight self weight (users, tools and materials)

For greater heights and loads, consult Youngman for guidance.

Platform Loading

On an 850, tower a platform comprises of a single deck only. The maximum safe working load (the combined weight of the users, tools and materials) that may be placed on a platform is 275kg, evenly distributed over the deck.

The quantities on pages 13 and 14, will enable BoSS towers to be built safely and therefore comply with the requirements of the Work at Height Regulations 2005. They include double guardrails to all platforms, and toeboards will need to be added if any levels are used as working platforms and for storage of materials.

EN 1004 requires platforms at least every 4.2m, and these measures will exceed that requirement.

Ballast : Internal / External Use

There is no requirement for ballast on 850 towers if using stabilisers as detailed in the table in the 850 quantity schedule.

Mobile Outriggers

MP16 outriggers can be used instead of SP15 stabilisers, as detailed below. Mobile outrigger kits comprise of:

Mobile Outrigger Kit
MP 16 Mobile Outrigger4
125/150/20mm Castor (Use same diaeter castors as on tower)4
250mm Adjustable Leg4
Plan Braces4
The above components replace: SP15 Stabiliser4

Stabilisers

To improve rigidity, larger stabilisers can be used at a lower level than shown in the quantity schedule.

Angle Of Stabiliser 850 Tower

Single Width 850 Tower Dimension X

Platform Length 1.8mPlatform Length 2.5m
SP7X = 2994X = 3201
SP10X = 4458X = 4734
SP15X = 5195X = 5485

Assembly Procedure - Mobile Towers - 3T Method

Assembly and Dismantling Procedures

Platform Height In MetresFrame At Base
1.7, 2.2, 3.7, 4.2, 5.7, 6.2, 7.7, 8.2, 9.7, 10.2, 11.7, 12.22 rung
2.7, 4.7, 6.7, 8.7, 10.73 rung
1.2, 3.2, 5.2, 7.2, 9.2, 11.24 rung

Where all 3 frame heights are used in a tower, start with 4 rung frames at the base, with the 6 rung frames next and the 8 rung frames on the top. Refer to the quantity schedules for detail.

To Dismantle A BoSS Ladderspan Tower

Checklist

|

Ensure horizontal braces and guardrails are fitted correctly. Always fit as shown.

Refer to this checklist before using each time.

Assembly Procedure - Mobile Towers 1450 3T Method

Assembly for 1450 Towers

Always start building with the smallest height frames at the base of the tower:

Platform Height In MetresFrame At Base
1.7, 2.2, 3.7, 4.2, 5.7, 6.2, 7.7, 8.2, 9.7, 10.2, 11.7, 12.22 rung
2.7, 4.7, 6.7, 8.7, 10.73 rung
1.2, 3.2, 5.2, 7.2, 9.2, 11.24 rung

Where all 3 frame heights are used in a tower, start with 4 rung frames at the base, with the 6 rung frames next and the 8 rung frames on the top. Refer to the Quantity Schedules for detail. The procedure illustrated shows 4.2m platform height tower starting with a 4 rung frame.

BoSS recommend two persons are used to build BoSS Towers. Above 4m height, it is essential that at least two persons are used. Only climb the tower from the inside.

Handrail

1:

Push 4 castors onto 4 adjustable legs. Insert adjustable legs into 2 end frames as shown. Lock castor brakes. Base plates can be fitted to adjustable legs if it is not necessary to move the tower.

Handrail

2:

Fit one horizontal brace (red) onto the vertical of an end frame, just above the bottom rung, with the claw facing outwards. Note: All locking claws must be opening before fitting.

Handrail

3:

Position the second end frame as shown and fit the other end of the horizontal brace onto the vertical, just above the bottom rung. Fit a second horizontal brace between the bottom rungs on the other side of the frames to square the tower.

Handrail

4:

Fit 2 additional end frames and check that the frame interlock clips are engaged. Fit 2 diagonal braces (blue) in opposing directions between the 2nd and the 6th rungs. Ensure the frames are vertical and level by checking with a spirit level and setting the adjustable legs as required. IMPORTANT - Only use the adjustable legs to level the tower and not to gain extra height.

Handrail

Fit Stabilisers

Handrail

5:

Fit a temporary deck on the lowest rungs. Fit a trapdoor deck on the 8th rung (2.0m) on one side of the tower. Ensure that the trapdoor is positioned with the hinges towards the outside of the tower as shown. Climb the end frame below the trapdoor on the inside of the tower, and from within the protected trapdoor position, fit horizontal braces on the 10th and 12th rungs (in that order) on both sides of the deck. Do not climb onto the deck until it is fully guardrailed. When horizontal braces are fitted as guardrails, they should be 0.5m and 1.0m (2 and 4 rungs) above the deck level. Remove the temporary deck from the lowest rung.

Handrail

6:

Fit the next pair of diagonal braces in opposing directions between the 6th and 10th rungs add 2 additional end frames.

Handrail

7:

Add two more diagonal braces between the 10th and 14th rungs. If finishing at this height (4.2m platform), the fixed deck should be repositioned to the 16th rung on the opposite side of the tower to the trapdoor deck. Fit a trapdoor deck alongside it with the hinges towards the outside of the tower and the trapdoor in line with the one below. Climb the tower and from the protected trapdoor position, fit the horizontal braces as guardrails on both sides at 2 and 4 rungs (0.5 and 1.0m) above the platform level. At the final level, a further diagonal braces should be added on one side of the tower as shown.

Handrail

8:

Continue to add pairs of end frames, diagonal braces and fit trapdoor decks as shown in the previous steps. At every platform level, add horizontal braces as guardrails at 2 and 4 rungs above the platform. Fit these guardrail braces from the protected trapdoor position. Do not climb onto the platform until it is fully guardrailed. Continue until the required height is reached. Re-position the fixed deck to the required platform height and fit a trapdoor deck alongside it as shown in Stage 7. Fir a single diagonal at the top of the tower as shown in Stage 7. Fit the guardrails as shown in Stage 7.

Handrail

9:

Fit toeboards. The tower is now complete.

Dismantling Procedure

To take down the tower, reverse the building sequence. When removing guardrail braces, unlock the claws furthest from the trapdoor and then return immediately to the protected position within the trapdoor. You may then unlock the claws at the other ends of the Guardrails to remove them from the tower.

Assembly Procedure - Mobile Towers 850 3T Method

Assembly for 850 Towers

Always start building with the smallest height frames at the base of the tower:

Platform Height In MetresFrame At Base
1.7, 2.2, 3.7, 4.2, 5.7, 6.2, 7.7, 8.2, 9.7, 10.2, 11.7, 12.24 rung
2.7, 4.7, 6.7, 8.7, 10.76 rung
1.2, 3.2, 5.2, 7.2, 9.2, 11.28 rung

Where all 3 Heights are used in a tower, start with 4 rung frames at the base, with the 6 rung frames next and the 8 rung frames on top. Refer to the quantity schedules for detail.

The procedure illustrated shows a tower starting with an 8 rung frame.

Handrail

1:

Insert adjustable leg/castor assemblies into end frames and lock the castors. Base plates can be fitted to the adjustable legs if it is not necessary to move the tower. Fit 2 horizontal braces to the 850 end frames as shown in steps 2 and 3 for the 1450 tower procedure. Ensure that the frames are vertical and level by checking with a spirit level and setting the adjustable legs required.

Handrail

2:

Fit a trapdoor deck on the 4th rung. Fix the horizontal braces (red) as guardrails on the 6th and 8th rungs (2 and 4 rungs above the platform) on both sides of the tower.

Handrail

3:

Fit 2 diagonal braces (blue) in opposing directions between the 2nd and 6th rungs. Ensure the frames are vertical and level by checking with a spirit level and setting the adjustable legs as necessary. Fit the next pair of end frames and check the frame interlock clips are engaged. Fit stabilisers.

Handrail

4:

Fit 2 pairs of diagonal braces in opposing directions between the 6th and 10th rungs and the 10th and 14th rungs. Locate a trapdoor deck on the 12th rung.

Handrail

5:

Climb up the inside of the tower and from the protected position of the trapdoor, fit horizontal braces as guardrails (on both sides) to the 14th and 16th rungs (2 and 4 rungs above the platform in that order).

Handrail

6:

Fit a trapdoor deck on the 4th rung. Fix the horizontal braces (red) as guardrails on the 6th and 8th rungs (2 and 4 rungs above the platform) on both sides of the tower.

Dismantling Procedure

To take down the tower, reverse the building sequence. When removing guardrail braces, unlock the 4 claws furthest from the trapdoor and return immediately to the protected position within the trapdoor and then return immediately to the protected position within the trapdoor. You may then unlock the claws at the other ends of the guardrails to remove them from the tower.

Fitting Toeboards

Lock yellow plastic toeboard clips over rung and deck claw as shown. Position as (A) on right hand deck claw. On other side of the working platform, position the clip as (B). Place 25mm thick toeboards into slots in toeboard clips as shown.

Lock yellow plastic toeboard clips over rung and deck claw as shown. Position as (A) on right hand deck claw. On other side of the working platform, position the clip as (B). Place 25mm thick toeboards into slots in toeboard clips as shown.

Stabilisers and Outriggers - Mobile Towers 3T method

Stabilisers

Attach one stabiliser to each corner of the tower as shown. Ensure stabiliser feet are equally spaced to form a square. SP10 and SP15 telescopic stabilisers must always be fully extended.

Position the lower clamp so that the lower arm is as close to the horizontal as possible. Adjust the position of the top clamp to ensure the stabiliser foot is in firm contact with the ground. Ensure clamps are secure.

Stabilisers are used when the tower is to be moved occasionally, frequent movement will require mobile outriggers.

When moving the tower, adjust the top clamps to lift the four stabiliser feet a maximum of 25mm off the ground and then unlock the castor brakes. After moving, ensure all four stabiliser feet are repositioned in firm contact with the ground.

Stabiliser Dimensions

Outriggers

For information on mobile outriggers please consult your supplier.

Branches

Trinity Street Off Tat Bank Road,

Oldbury, West Midlands, B69 4LA

T: 0121 544 3355 F: 0121 544 3131

E: birmingham@generationuk.co.uk

87-93 Amington Road,

Birmingham, West Midlands, B25 8ETT

T: 0121 706 0000 F: 0121 706 9832

E: birminghameast@generationuk.co.uk

Unit 7, 12-16 Foundry Lane, Fishponds,

Bristol, BS5 7UE

T: 0117 972 4550 F: 0117 972 4502

E: bristol@generationuk.co.uk

Martin Road, Tremorfa Industrial Estate,

Cardiff, CF24 5SD

T: 029 2046 3835 F: 029 2046 3246

E: cardiff@generationuk.co.uk

4 Westerton Road,

East Mains Industrial Estate, Broxburn,

West Lothian, EH52 5AU

T: 01506 863 864 F: 01506 863 916

E: edinburgh@generationuk.co.uk

22-30 Sturt Road, Frimley Green

Camberley, GU16 6HY

T: 01252 838 696 F: 01252 837 614

E: frimley@generationuk.co.uk

Stoneygate Lane, Abbotsford Road,

Felling, Gateshead, NE10 0EX

T: 0191 469 7504 F: 0191 469 8237

E: gateshead@generationuk.co.uk

Duchess Road, Rutherglen

Glasgow, G73 1AU

T: 0141 647 6969 F: 0141 647 5851

E: glasgow@generationuk.co.uk

Europa Business Park, Magnet Road,

Grays, Essex, RM20 4DB

T: 01375 312 120 F: 01375 386 844

E: grays@generationuk.co.uk

Unit 2 Ledger Park, Haigh Park Road,

Stourton, Leeds LS10 1RT

T: 0113 277 8822 F: 0113 277 7545

E: leeds@generationuk.co.uk

Unit H, Hangman’s Wood Ind Park,

Stifford Road, South Ockendon,

Essex, RM15 6RL

T: 020 7473 6056 F: 01708 858 493

E: london@generationuk.co.uk

Forward House, Portobello Road

Portobello Industrial Estate, Birtley,

Tyne and Wear, DH3 2SN

T: 0191 492 1190 F: 0191 411 1148

E: newcastle@generationuk.co.uk

Kingsfield Way, Dallington,

Northampton, NN5 7QN

T: 01604 580 444 F: 01604 580 487

E: northampton@generationuk.co.uk

Duntilland Road, Shotts, Salsburgh,

North Lanarkshire, ML7 4NZ

T: 01698 870 200 F: 01698 870 159

E: salsburgh@generationuk.co.uk

Unit 4 Vauxhall Industrial Estate,

Greg Street, Reddish,

Stockport, SK5 7BR

T: 0161 477 0131 F: 0161 477 7618

E: stockport@generationuk.co.uk

4 Riverside Ind. Park, Oliver Road,

West Thurrock, RM20 3ED

T: 020 7476 4760 F: 020 7476 3157

E: westthurrock@generationuk.co.uk

Pitt Street, West Bank, Widnes,

Cheshire, WA8 0TG

T: 0151 420 3331 F: 0151 495 2298

E: widnes@generationuk.co.uk

Unit 20B Greens Industrial Park,

Calder Vale Road, Wakefield, WF1 5PH

T: 01924 370 640

T: 0800 587 5224

E: training@altraduk.co.uk

Trinity Street, Off Tat Bank Road

Oldbury, West Midlands, B69 4LA

T: +44 (0) 121 543 2964

E: export@generationuk.co.uk

Trinity Street, Off Tat Bank Road

Oldbury, West Midlands, B69 4LA

T: 0121 543 2950 F: 0121 543 2953

E: enquiries@generationuk.co.uk